December 2025 · Storage

Otopeni BESS obtains 110 kV grid connection

The 40 MW / 160 MWh standalone storage project near Bucharest has received its grid connection permit (ATR).

Project

  • 4-hour LFP battery storage
  • 110 kV connection to the distribution grid
  • Balancing, ancillary services and arbitrage

Next steps

  • Connection contract and grid works
  • EPC selection
  • Financing